Time and Work Type 5 (Tricky Approach)

Time and Work Type 5 (Tricky Approach)

Example 9 : The work capacity of A is 60% more than the work capacity of B. A Alone can do this work in 80 days, so how long B alone will this work ?

  • Start same as previous examples then it is Efficiency based problem. In this problem first we find ratio of the Efficiency of A and B
  • A : B = 160 : 100 = 8 : 5
  • Write their efficiency, A can do 8 works in a day so in 80 days he will do 640 (total work) or you can remember when go upward multiply and when come downward divide.
  • For B we go downward so 640/5= 128 days

Example 9

Example 10: The work capacity of A is 25% less than the work capacity of B, and the work capacity of B is 20% more than the work capacity of C. Together, the three can finish this task in 36 days, so how long B will do this work alone ?

  • Start same as previous examples then it is Efficiency based problem. In this problem first we find ratio of the Efficiency of A and B
  • A : B = 75 : 100 = 3 : 4
  • B : C = 120 : 100 = 6 : 5

Example 10

  • So A,B and C can do 31 work in a day, they work for 36 days so total work done by them is = 31x36. We will write total work on top and for finding work done by B alone we simply divide total work by one day work of B ie: 12.

Example 10-2

Time and Work Type 7 (Tricky Approach) Study Notes
Time and Work Type 7 (Tricky Approach)Example 12: . A,B and C can finish one work in 12, 15, 20 days respectively. All three of them together start work...
  Admin
  Jun 8th 2019
Time and Work Type 6 (Tricky Approach) Study Notes
Time and Work Type 6 (Tricky Approach)Example 10: . A can do 2/5 of any work in 6 days and B can do 1/3 part of the work in 10 days then both of them...
  Admin
  Jun 8th 2019
TIME AND WORK TYPE 1
TIME AND WORK TYPE 1This chapter is based on the concept of direct and inverse variations. We need to understand relation among time, work done and number...
  Admin
  Jun 8th 2019
Time And Work Type 2
Time And Work Type 2This chapter is based on the concept of direct and inverse variations. We need to understand relation among time, work done and number...
  Admin
  Jun 8th 2019
Time and Work Type 3 (Tricky Approach) Study Notes
Time and Work Type 3 (Tricky Approach)Example 5 : A and B together can complete a task in 20 days. B and C together can complete the same task in 30 days....
  Admin
  Jun 8th 2019
Time and Work Type 5 (Tricky Approach)
Time and Work Type 5 (Tricky Approach)Example 9 : The work capacity of A is 60% more than the work capacity of B. A Alone can do this work in 80 days,...
  Admin
  Jun 8th 2019