Time and Work Type 6 (Tricky Approach)

Example 10: . A can do 2/5 of any work in 6 days and B can do 1/3 part of the work in 10 days then both of them will work 4/5 of the work in how many days.?

  • A can do 2/5 of any work in 6 days so whole work done by A in = 6 x 5/2=15 days
  • B can do 1/3 part of the work in 10 days so whole work done by B in 10 x 3= 30 days

Time and Work Type 6

  • Now 4/5 of the work 30 x4/5= 24 work
  •  A and B can do 3 work in a day so 24/3=8 days

Example 11: . A can do 2/5 of any work in 8 days and B can do 2/3 part of the work in 10 days then both of them will work 4/5 of the work in how many days.?

Please write answer in comment box